As Passed by the House

135th General Assembly

Regular Session Sub. H. B. No. 79

2023-2024

Representatives Seitz, Sweeney

Cosponsors: Representatives Weinstein, Isaacsohn, Hoops, Klopfenstein, Upchurch, McNally, Brennan, Carruthers, Dell'Aquila, Skindell, Miller, A., Abdullahi, Brent, Brewer, Brown, Cross, Dobos, Jarrells, Liston, Robb Blasdel, Russo, Somani, Troy, Whitted


A BILL

To amend section 4928.02 and to enact sections 4928.6630, 4928.6631, 4928.6633, 4928.6634, 4928.6635, 4928.6636, 4928.6637, 4928.6639, 4928.6641, 4928.6642, 4928.6644, 4928.6645, 4928.6646, 4928.6647, 4928.6650, 4928.6653, 4928.6655, 4928.6657, 4928.6660, and 4928.6665 of the Revised Code to permit electric distribution utilities to establish energy efficiency and demand reduction portfolios.

BE IT ENACTED BY THE GENERAL ASSEMBLY OF THE STATE OF OHIO:

Section 1. That section 4928.02 be amended and sections 4928.6630, 4928.6631, 4928.6633, 4928.6634, 4928.6635, 4928.6636, 4928.6637, 4928.6639, 4928.6641, 4928.6642, 4928.6644, 4928.6645, 4928.6646, 4928.6647, 4928.6650, 4928.6653, 4928.6655, 4928.6657, 4928.6660, and 4928.6665 of the Revised Code be enacted to read as follows:

Sec. 4928.02. It is the policy of this state to do the following throughout this state:

(A) Ensure the availability to consumers of adequate, reliable, safe, efficient, nondiscriminatory, and reasonably priced retail electric service;

(B) Ensure the availability of unbundled and comparable retail electric service that provides consumers with the supplier, price, terms, conditions, and quality options they elect to meet their respective needs;

(C) Ensure diversity of electricity supplies and suppliers, by giving consumers effective choices over the selection of those supplies and suppliers and by encouraging the development of distributed and small generation facilities;

(D) Encourage innovation and market access for cost-effective supply- and demand-side retail electric service including, but not limited to, demand-side management, time-differentiated pricing, waste energy recovery systems, smart grid programs, and implementation of advanced metering infrastructure;

(E) Encourage cost-effective and efficient access to information regarding the operation of the transmission and distribution systems of electric utilities in order to promote both effective customer choice of retail electric service and the development of performance standards and targets for service quality for all consumers, including annual achievement reports written in plain language;

(F) Ensure that an electric utility's transmission and distribution systems are available to a customer-generator or owner of distributed generation, so that the customer-generator or owner can market and deliver the electricity it produces;

(G) Recognize the continuing emergence of competitive electricity markets through the development and implementation of flexible regulatory treatment;

(H) Ensure effective competition in the provision of retail electric service by avoiding anticompetitive subsidies flowing from a noncompetitive retail electric service to a competitive retail electric service or to a product or service other than retail electric service, and vice versa, including by prohibiting the recovery of any generation-related costs through distribution or transmission rates;

(I) Ensure retail electric service consumers protection against unreasonable sales practices, market deficiencies, and market power;

(J) Provide coherent, transparent means of giving appropriate incentives to technologies that can adapt successfully to potential environmental mandates;

(K) Encourage implementation of distributed generation across customer classes through regular review and updating of administrative rules governing critical issues such as, but not limited to, interconnection standards, standby charges, and net metering;

(L) Protect at-risk populations, including, but not limited to, when considering the implementation of any new advanced energy or renewable energy resource;

(M) Encourage the education of small business owners in this state regarding the use of, and encourage the use of, energy efficiency programs and alternative energy resources in their businesses;

(N) Encourage electric distribution utilities to develop voluntary portfolios of energy savings programs to help their customers to save energy;

(O) Facilitate the state's effectiveness in the global economy.;

(O) (P) Encourage cost-effective, timely, and efficient access to and sharing of customer usage data with customers and competitive suppliers to promote customer choice and grid modernization.;

(P) (Q) Ensure that a customer's data is provided in a standard format and provided to third parties in as close to real time as is economically justifiable in order to spur economic investment and improve the energy options of individual customers.

In carrying out this policy, the commission shall consider rules as they apply to the costs of electric distribution infrastructure, including, but not limited to, line extensions, for the purpose of development in this state.

Sec. 4928.6630. As used in sections 4928.6630 to 4928.6665 of the Revised Code:

"Behavioral energy savings" means energy savings that occurs as a result of a change in a residential retail electric customer's pattern of electricity use.

"Nonresidential retail customer" means a customer that is not a residential customer or a mercantile customer.

"Energy savings" includes energy efficiency savings and peak demand reduction savings.

Sec. 4928.6631. An electric distribution utility may submit an application to the public utilities commission for approval of a portfolio of energy savings programs to assist retail electric customers in achieving energy savings.

Sec. 4928.6633. An electric distribution utility's application for a portfolio shall include the following information about the energy savings programs proposed for the portfolio:

(A) Descriptions of the size and scope of the programs;

(B) The programs' costs, planned energy savings, and cost-effectiveness;

(C) The utility's projection of the expected number of customers opting out of the programs under section 4928.6657 of the Revised Code;

(D) The program costs, availability, and planned energy savings listed by programs for residential customer and nonresidential retail customer classes and any programs that could impact all customer classes;

(E)(1) Proposed mechanisms for:

(a) The recovery of program costs, excluding internal utility employee labor costs already being recovered in the utility's rates established under its most recent rate case under section 4909.18 of the Revised Code;

(b) Utility incentives;

(c) One of the following mechanisms, which the public utilities commission shall determine pursuant to section 4928.6634 of the Revised Code:

(i) A mechanism for the recovery of lost distribution revenues, if applicable;

(ii) Any mechanism under division (D) of section 4928.66 of the Revised Code.

A mechanism described in division (E)(1)(c) of this section collected for a particular year may only be collected for a period that shall not exceed the length of the term of the portfolio approved by the public utilities commission.

(2) If applicable, any lost distribution revenue mechanism approved under division (E)(1)(c) of this section shall be normalized for weather. No mechanism approved under this section may result in any double recovery.

(F) A plan to improve the following:

(1) Customers' smart technology capability for demand side management;

(2) Utility control to reduce demand or impacts of intermittent resources on the grid, which plan shall require working in coordination with electric services companies.

(G) A description of how the portfolio will meet the requirements under section 4928.6636 of the Revised Code;

(H) If the financial parameters described in section 4928.6647 of the Revised Code do not allow the portfolio design to be consistent with the energy savings measures under section 4928.6639 of the Revised Code, an explanation of why consistency is not possible;

(I) Any other information that the utility determines is appropriate for commission review.

Sec. 4928.6634. (A) The public utilities commission shall conduct hearings on a portfolio application.

(B) Not later than one hundred eighty days after receiving an application under section 4928.6631 of the Revised Code, the commission shall issue an order to approve or modify and approve the application, if the commission finds that the application meets the requirements under section 4928.6633 of the Revised Code and includes the program required under section 4928.6636 of the Revised Code, and shall deny the application if these requirements are not met. The commission may modify an application only as necessary for the application to comply with sections 4928.6633, 4928.6639, 4928.6641, 4928.6642, 4928.6644, 4928.6647, and 4928.6653 of the Revised Code. In its approval of an application filed pursuant to section 4928.6631 of the Revised Code, the commission shall specify according to established rate classes the use of either lost distribution revenue recovery or recovery under division (D) of section 4928.66 of the Revised Code.

An order by the commission approving or modifying and approving an application shall authorize accounting mechanisms under which the utility may defer and recover only those commission-approved program costs that would cause the utility to recover in excess of the rate caps under section 4928.6650 of the Revised Code due to a level of customer participation in the program that exceeded the utility's expectations.

(C) Not later than ninety days after the date of the commission's final order, the utility shall accept the modified application or withdraw the application if either or both of the following occurs:

(1) The commission modifies and approves the application.

(2) A higher than expected number of customers opt out of the portfolio.

(D) A portfolio approved by the commission shall be for a term of not more than five years. To replace or extend a portfolio that is terminating, a utility shall file a new portfolio application with the commission.

Sec. 4928.6635. (A) As used in this section, "proceeding" means a proceeding relating to a portfolio application under section 4928.6634 of the Revised Code.

(B) No electric distribution utility or its affiliate may do either of the following to induce any party to a proceeding to enter into a settlement of a proceeding pending before the commission:

(1) Make a cash payment to that party that is not specifically tied to the provision of services related to the utility offering energy efficiency programs;

(2) Enter into any agreement or any financial or private arrangement with that party that is not made part of the public case record.

Sec. 4928.6636. An electric distribution utility portfolio approved under section 4928.6634 of the Revised Code shall include at least one program planned to benefit low-income residential customers with an annual income at or below two hundred per cent of the federal poverty level. Total proposed residential program costs for programs projected to reach low-income residential customers pursuant to this section shall be not less than fifteen per cent of the total program costs proposed for all residential programs in the portfolio.

Sec. 4928.6637. (A) As used in this section, "trade allies" means entities that, on behalf of a customer participating in an electric distribution utility's energy efficiency program, install equipment or measures that qualify for an incentive included in a portfolio approved under section 4928.6634 of the Revised Code.

(B) An electric distribution utility portfolio approved under section 4928.6634 of the Revised Code shall include provisions intended to reasonably accommodate the participation of small businesses as trade allies in all the counties within the electric distribution utility's service area under the utility's proposed energy efficiency programs.

Sec. 4928.6639. An electric distribution utility portfolio shall be designed to do the following:

(A) Achieve gross annual energy savings of at least one-half of one per cent of the gross annual energy savings of the prior year's retail electric sales to participating customers, except as limited by the requirement under section 4928.6647 of the Revised Code;

(B) Achieve not more than thirty per cent of the planned annual gross energy savings through residential programs designed to deliver only behavioral energy savings;

(C) Emphasize smart technology measures, including, but not limited to, appliance controllers and energy star qualified smart thermostats;

(D) Determine gross energy savings as follows:

(1) Directly through standard evaluation, measurement, and verification protocols, such as a bill savings analysis, or, if available, through metering that has the capability to measure demand in kilowatts;

(2) For gross energy savings not determined directly pursuant to division (D)(1) of this section, with a baseline established for federal energy standards for appliances and other equipment or standards under the Ohio building code under Chapter 3781. of the Revised Code;

(3) For demand savings when residential advanced metering is not available, the amount of kilowatt hours shifted to periods other than periods of high demand, if this method of determining gross energy savings is included in the approved portfolio.

(E) For gross energy savings determined under division (D)(2) of this section, only permit customer incentives on equipment that exceeds federal energy standards or Ohio building code standards;

(F) Exclude gross energy savings from any physical device or equipment that has not been enrolled in the program with the permission or at the request of a participating customer.

(G) For gross energy savings determined under division (D)(2) of this section, the utility shall only claim savings for equipment in cases in which it has paid a customer incentive.

Sec. 4928.6641. An electric distribution utility's portfolio under sections 4928.6630 to 4928.6665 of the Revised Code shall be cost-effective based on a utility cost test that compares the total cost of the portfolio's measurable programs to any of the following:

(A) Avoided electric generation, transmission, and distribution costs;

(B) Reductions in market prices for energy and capacity;

(C) Reductions in utility credit and collection costs;

(D) Any other quantifiable utility system benefits.

Sec. 4928.6642. An electric distribution utility's portfolio under sections 4928.6630 to 4928.6665 of the Revised Code shall ensure that any savings on a customer's monthly bill or reduction in energy usage that are the result of the customer's participation in any federal energy efficiency program or use of a federal tax rebate or credit shall not be attributed to the utility's programs.

Sec. 4928.6644. Customer incentives offered by an electric distribution utility through a portfolio under sections 4928.6630 to 4928.6665 of the Revised Code shall provide a meaningful inducement for customers to participate in the cost-effective delivery of projected energy savings. Utility incentives through such a portfolio shall not exceed ten per cent of actual program costs, on an after-tax basis and excluding any advertising or marketing dollars, and shall not count toward the net cost of the portfolio under section 4928.6647 of the Revised Code or the rate caps under section 4928.6650 of the Revised Code. The public utilities commission may adopt rules to implement this section.

Sec. 4928.6645. If an electric distribution utility with a portfolio approved by the public utilities commission under sections 4928.6630 to 4928.6665 of the Revised Code produces or pays for any advertisement or marketing material to promote energy savings programs established under the portfolio, the advertisement or marketing material shall include a description of the specific energy savings programs that the utility is promoting and offering to its customers.

Sec. 4928.6646. The recovery of any revenue through either mechanism described in division (E)(1)(c) of section 4928.6633 of the Revised Code under an electric distribution utility portfolio approved under section 4928.6634 of the Revised Code shall not count toward the net cost of the portfolio under section 4928.6647 of the Revised Code or the rate caps under section 4928.6650 of the Revised Code. The recovery of any revenue through any such mechanism is not subject to sections 4928.6655 and 4928.6657 of the Revised Code.

Sec. 4928.6647. The net cost of an electric distribution utility's portfolio under sections 4928.6630 to 4928.6665 of the Revised Code shall not exceed two and one-quarter per cent of the difference between the utility's annual total electric operating revenues for the previous year as reported in the utility's FERC financial report, FERC form 1, account 400, required by the federal energy regulatory commission less the purchased power expense, account 555, for the same year. The utility's net cost equals the utility's total program costs for a portfolio approved by the public utilities commission minus eighty per cent of any revenues the utility collects during the same program year from capacity, environmental, and other attributes of the utility's energy savings programs, including bidding efficiency into the wholesale market operated by PJM interconnection, L.L.C. The utility shall retain twenty per cent of revenues received from program energy savings that are bid into the wholesale market, which revenues shall be separate from utility incentives described in section 4928.6644 of the Revised Code.

Sec. 4928.6650. (A) A utility's portfolio costs shall not result in a rate that produces a monthly charge for residential customers that is greater than one dollar and fifty cents per customer per month or for nonresidential retail customers that is greater than seven dollars and fifty cents per customer per month.

(B) If a higher than expected number of residential customers opt out of the portfolio under section 4928.6657 of the Revised Code, the utility automatically is authorized to reduce spending under its approved portfolio to ensure that the utility complies with division (A) of this section.

Sec. 4928.6653. The following applies to gross annual energy savings from transmission and distribution system investments that result in measurable energy savings:

(A) The investments shall not be considered to be a program within an electric distribution utility portfolio under sections 4928.6630 to 4928.6665 of the Revised Code for cost recovery and incentive purposes under the portfolio.

(B) The energy savings shall count toward determining whether the utility achieved its annual gross energy savings required under division (A) of section 4928.6639 of the Revised Code.

Sec. 4928.6655. (A) Mercantile customers shall be automatically opted out of any opportunities to participate in an electric distribution utility's portfolio and any portfolio cost recovery unless they affirmatively choose to opt in to the utility's portfolio in writing.

(B) After the public utilities commission approves a utility's portfolio under section 4928.6634 of the Revised Code, the utility shall send, to all mercantile customers in its certified territory, a written notice describing the option for such customers to affirmatively opt in to portfolio participation.

(1) The opt-in notice shall provide the cost of participating in the portfolio to the mercantile customer.

(2) A mercantile customer submitting a written opt-in application, as prescribed by the utility, shall be deemed to have opted in.

(C) Mercantile customers that opt in shall remain as an opt-in customer for a period of not less than twelve months from the date the customer first receives the benefit of participation.

Sec. 4928.6657. (A) At the start of a new portfolio, an electric distribution utility that has a portfolio approved under section 4928.6634 of the Revised Code shall provide residential customers and nonresidential retail customers with the option to opt out of portfolio participation and cost recovery for the portfolio or, for customers that have previously opted out, to opt in to such participation. Within five business days after a portfolio is approved by the public utilities commission, the utility shall send, to all residential customers and nonresidential retail customers in its certified territory, a written notice describing the options to opt out of and opt back in to participation in the portfolio. Within thirty days after the portfolio's approval, the utility shall send, to the residential customers and nonresidential retail customers, a second written notice with the same content as the first notice. The time period during which a customer may opt out of, or opt in to, participation shall extend at least forty-five days from the date of the postmark on the first written notice. If a customer, as prescribed by the utility, indicates the customer's intent to opt out or opt in before the deadline has elapsed, the customer shall be deemed to have opted out or opted in, as applicable.

(B) The opt-out and opt-in process shall permit customers to express the intent to opt out or to opt in by returning a postcard or similar notice to the utility. The process also shall include alternative methods, such as a telephonic or an internet method, provided that these alternative methods allow for a verification of the customer's election to opt out or opt in.

(C) If, upon the expiration of its term, a portfolio is renewed or if a new portfolio is approved by the commission, a customer's election to opt out of participation in a previous portfolio pursuant to division (A) of this section remains in effect until the customer elects to opt in as prescribed in the notices required under division (A) of this section.

Sec. 4928.6660. An electric services company that promotes energy savings and the use of electric distribution utility energy savings programs shall be eligible to be considered a third party to whom the customer may convey an energy savings incentive associated with participation in a utility energy savings program if all of the following are true:

(A) The electric services company has obtained the customer's written consent.

(B) The electric services company has verified the customer's identity by providing the customer's electric distribution utility account number or service delivery identifier number.

(C) The electric services company has explained how the incentive being conveyed meets the energy savings program eligibility requirements.

(D) The electric services company produces evidence that the customer completed the program. This evidence may be in the form of a product identification code, product serial number, or similar evidence that proves installation or delivery of an eligible product under the energy savings program.

Sec. 4928.6665. (A) An electric distribution utility's portfolio approved by the public utilities commission under section 4928.6634 of the Revised Code shall be subject to an annual cost-effectiveness and compliance review over the term of the portfolio. As part of the annual review, the utility shall review the cost-effectiveness of its portfolio according to the utility cost test and inputs described in section 4928.6641 of the Revised Code and ensure the requirements of section 4928.6642 of the Revised Code are met. Based on the cost-effectiveness review, the utility may update its portfolio as needed.

(B) Not later than the fifteenth day of April each year, the utility shall file with the commission a report of its annual review for the preceding year.

(C) Not later than July 1, 2026, and every three years thereafter, the commission shall review each report received pursuant to division (B) of this section and, in accordance with section 101.68 of the Revised Code, submit a report to the general assembly that includes a compilation of utility reports received and an overview of utility compliance and energy savings.

(D) Based on the results of the commission's review of a utility's report, reasonable costs for evaluation, measurement, and verification for each utility's program shall be recovered through the affected utility's portfolio cost recovery mechanism. Such costs shall not be considered as portfolio costs or included in any calculations required under section 4928.6647 of the Revised Code or the rate caps under section 4928.6650 of the Revised Code.

(E) During the review under this section and subject to the general assembly's findings regarding the utility's performance and compliance described in the commission's report, the utility shall continue to offer customers a portfolio of energy savings programs.

Section 2. That existing section 4928.02 of the Revised Code is hereby repealed.